Thailand · Chiang Mai (Chiang Mai University) · 2026

Chiang Mai, Thailand: smart agrivoltaics for coffee and napa cabbage

29.2 kW · Under construction

Example photo: the fixed agrivoltaic installation Chiang Mai University built earlier on its campus. The new tracking plant goes up at the end of 2026.

Example photo: the fixed agrivoltaic installation Chiang Mai University built earlier on its campus. The new tracking plant goes up at the end of 2026.

Thailand drinks more coffee every year, and its farms cannot keep up, so much of the bean is imported. Coffee is at home beneath a tree canopy, which makes it a natural match for the shade of a panel. KLES and ENVELOPS signed a research MoU with Chiang Mai University’s Faculty of Agriculture and its Energy Research and Development Institute in October 2025, and in August 2026 the two institutes confirmed a site and joint research in a letter of intent. A 29.2 kWp smart agrivoltaic pilot is being built under Korea South-East Power’s 2026 Global Testbed programme. The foundations are in, the plant goes up at the end of 2026, and the pilot is due to run in the first half of 2027. KLES leads the project. ENVELOPS provides the crop- and site-specific concept design, SAMS, and crop planning and management.

The crops under the shade

The new plant is a tracking structure that changes its panel angle, and it will be compared side by side with the campus’s existing fixed agrivoltaic installation and with open ground. Shade-loving robusta coffee goes in with winter napa cabbage between the rows, and vanilla, which wants deeper shade, is being considered for the existing fixed installation. A kimchi made from Chiang Mai napa cabbage, with the carbon taken out of both the growing and the power, is this site’s story in miniature. Generation, crop and microclimate data will run through SAMS, and the results will be written up with the university.

Agrivoltaics as farm infrastructure

The electricity can go on to irrigation, cold storage, processing and EV charging. One plant running a whole farming cycle on renewable energy: that is what the Chiang Mai pilot sets out to show next.

Country
Thailand · Chiang Mai (Chiang Mai University)
Year
2026
Capacity
29.2 kW
Crops
Napa cabbage, coffee, vanilla
ENVELOPS role
Design, Operation & SAMSConcept design, SAMS, crop planning and management (a KLES-led project)
Partners
Faculty of Agriculture, Chiang Mai University (AGRI-CMU), Energy Research and Development Institute-Nakornping, Chiang Mai University (ERDI-CMU), KLES
Funders
Korea South-East Power 2026 Global Testbed Support Programme
Status
Under construction